(a)   This section applies only to a gas company, electric company, or
telephone company whose gross annual revenues, for the most recent
calendar year for which data are available, are less than 3% of the
total gross annual revenues of all public service companies in the
State during the same calendar year.
  (b)   (1)   When the Commission suspends a proposed new rate for a company subject
to this section that is based on the existing authorized fair rate of
return, the Commission promptly shall institute proceedings to
determine if additional revenues are required to allow the company to
earn the existing fair rate of return authorized in the previous base
rate proceeding.
    (2)   The Commission shall:
      (i)   serve each of the parties to the previous base rate proceeding of that
company with a copy of the suspension order; and
      (ii)   order the company to publish a display advertisement about the proposal
in newspapers of general circulation in its service area.
    (3)   Proceedings under this section shall:
      (i)   account for revenues, expenses, and rate base in the same manner that
the Commission employed in determining a just and reasonable rate in
the previous base rate proceeding; and
      (ii)   exclude consideration of any increase in the rate of return, any change
in rate structure, or any change in an accounting approach to any item
pertaining to revenues, expenses, or rate base inconsistent with that
used by the Commission in determining a just and reasonable rate in the
previous base rate proceeding on the company.
    (4)   In proceedings under this section, the Commission may use a more recent
past test period than that used in the previous base rate proceeding
for the company.
    (5)   The Commission shall enter a final order as to the revenue requirement
determined under this section within 90 days after the proposed new
rate is filed.
    (6)   The final order shall:
      (i)   authorize a new rate distributing any change in the revenue requirement
proportionally among the ratepayers without change in the rate
structure; and
      (ii)   state whether further proceedings shall be held.
    (7)   If, in the final order, the Commission decides to conduct further
proceedings under subsection (c) of this section, the final order may
provide for refund, consistent with the provisions of § 4-204(c) of
this subtitle, of any difference between the new rate authorized under
this subsection and the rate the Commission sets under subsection (c)
of this section.
  (c)   (1)   If the Commission decides to conduct further proceedings under
subsection (b) of this section, the Commission, after a hearing, may:
      (i)   modify the rate structure;
      (ii)   lower the authorized fair rate of return; or
      (iii)   modify the accounting approach to an item that pertains to revenues,
expenses, or rate base.
    (2)   The Commission shall take any action under this subsection within 120
days after entry of a final order under subsection (b) of this section.
  (d)   (1)   This section does not apply to a proposed new rate that is filed:
      (i)   less than 1 year after a previously proposed new rate under this
section is filed; or
      (ii)   with a request for temporary rates under § 4-205 of this subtitle.
    (2)   (i)   A company may not file a proposed new rate under this subtitle if any
proposed new rate filed by the company under this section is pending,
or a new rate filed by the company under this section has been in
effect fewer than 90 days.
      (ii)   This paragraph does not preclude a company from filing a proposed new
rate for a new service if the proposal does not affect the authorized
rate of return.
    (3)   Unless the Commission provides otherwise, this section does not apply
to a proposed new rate that is filed more than 3 years after the
Commission enters a final order authorizing the existing fair rate of
return in the previous base rate proceeding.
|